ESR13 Giuseppe Tilocca at Tirreno
After an initial visit to the power plant and the UNIGE “Innovative Energy System Laboratory” located
inside the Tirreno Power area, the main topics covered in the secondment were:
• Review of Capacity Remuneration Mechanism issued in the Italian Market and of regulatory
schemes for pilot projects for additional sources of flexibility. Focus on evolution on RES and
Storage regulation.
• General aspects of the hydroelectric production in Italy and its impact on local communities.
Insights on the operations of hydroelectric power, including Storage and production.
• Commercial relationships between large energy producers and CCGT OEMs and comparisons
with the MGT case.
• Evaluation of the equipment competitiveness, vendor rating and product fitness-to-application
from the buyer perspective.